Stockyard Hill Windfarm
Client : Sol Systems Pty Ltd (for Goldwind Australia)
Location : Beaufort, Victoria
March 2020 to present
The Windfarm comprises 149 WTG's with rated a capacity of 550MW. Three 132/33kV Substations, Balance of Plant, STATCOMs and Harmonic Filters.
Sol Systems completed the testing and commissioning of all primary and secondary plant and system.
Location : Beaufort, Victoria
March 2020 to present
The Windfarm comprises 149 WTG's with rated a capacity of 550MW. Three 132/33kV Substations, Balance of Plant, STATCOMs and Harmonic Filters.
Sol Systems completed the testing and commissioning of all primary and secondary plant and system.
![](https://static.wixstatic.com/media/399100_305c8a26daaf4040931999b12d6ae068~mv2.jpg/v1/fit/w_250,h_250,q_30,blur_30/399100_305c8a26daaf4040931999b12d6ae068~mv2.jpg)
![](https://static.wixstatic.com/media/399100_305c8a26daaf4040931999b12d6ae068~mv2.jpg/v1/fill/w_324,h_214,q_90/399100_305c8a26daaf4040931999b12d6ae068~mv2.jpg)
Cape Lambert Power Station & 220kV CLBSS Substation
Client : ABB & RCR (for Rio Tinto Iron Ore)
Location : Western Australia
June to December 2017
Expansion of RTIO's existing 220kV Cape Lambert substation to include two LM6000 PF SPRINT OCGT 65MVA Generator units.
CLPS was connected to the RTIO network via two 220/11kV power transformers & 220kV GIS switchgear.
ABB undertook the integration and modification of existing substation systems, acceptance testing and commissioning.
Location : Western Australia
June to December 2017
Expansion of RTIO's existing 220kV Cape Lambert substation to include two LM6000 PF SPRINT OCGT 65MVA Generator units.
CLPS was connected to the RTIO network via two 220/11kV power transformers & 220kV GIS switchgear.
ABB undertook the integration and modification of existing substation systems, acceptance testing and commissioning.
![](https://static.wixstatic.com/media/399100_23e0835d9fad4ea395c471ffe24b51e8~mv2.jpg/v1/fit/w_250,h_250,q_30,blur_30/399100_23e0835d9fad4ea395c471ffe24b51e8~mv2.jpg)
![](https://static.wixstatic.com/media/399100_23e0835d9fad4ea395c471ffe24b51e8~mv2.jpg/v1/fill/w_323,h_214,q_90/399100_23e0835d9fad4ea395c471ffe24b51e8~mv2.jpg)
SVC Installation and Maintenance
Electric Arc Furnace upgrade HV reticulation upgrades
Client : InfraBuild Steel
Location : Laverton North, Victoria
2009 to present
Installation, commissioning, maintenance and operational support of +115MVar SVC.
Protection and control system development to update existing scheme to digital protection with a focus on system reliability and improving information available to operators.
90 MVA EAF transformer upgrade and integration.
75 MVA Sydney Steel Mill EAF transformer installation & integration.
Client : InfraBuild Steel
Location : Laverton North, Victoria
2009 to present
Installation, commissioning, maintenance and operational support of +115MVar SVC.
Protection and control system development to update existing scheme to digital protection with a focus on system reliability and improving information available to operators.
90 MVA EAF transformer upgrade and integration.
75 MVA Sydney Steel Mill EAF transformer installation & integration.
![](https://static.wixstatic.com/media/399100_15014ad33d054efbaedea5959e8ba5a1~mv2.jpg/v1/fit/w_250,h_250,q_30,blur_30/399100_15014ad33d054efbaedea5959e8ba5a1~mv2.jpg)
![](https://static.wixstatic.com/media/399100_15014ad33d054efbaedea5959e8ba5a1~mv2.jpg/v1/fill/w_323,h_242,q_90/399100_15014ad33d054efbaedea5959e8ba5a1~mv2.jpg)
Eastern Treatment Plant
6.6kV 17H Influent Pump Station Switchboard replacement
Client : John Holland (for Melbourne Water)
Melbourne Victoria
2017
The HV switchboards for the pump station were being replaced with new ABB ZS1 equipment.
Testing and commissioning, remote end protection design and integration in brownfield environment.
Client : John Holland (for Melbourne Water)
Melbourne Victoria
2017
The HV switchboards for the pump station were being replaced with new ABB ZS1 equipment.
Testing and commissioning, remote end protection design and integration in brownfield environment.
![](https://static.wixstatic.com/media/399100_7e95792117fb43aaab32c9026b05fae5~mv2.jpg/v1/fit/w_250,h_250,q_30,blur_30/399100_7e95792117fb43aaab32c9026b05fae5~mv2.jpg)
![](https://static.wixstatic.com/media/399100_7e95792117fb43aaab32c9026b05fae5~mv2.jpg/v1/fill/w_324,h_243,q_90/399100_7e95792117fb43aaab32c9026b05fae5~mv2.jpg)
Rapid Earth Fault Current Limiter Upgrade (REFCL)
GridMec (for Powercor Australia)
Victoria
May 2018 to present
As part of the REFCL program it was a requirement for HV customers were adequately protected from the newly installed Rapid Earth Fault Limiters. The solution involved 22/22kV isolation kiosks with a power transformer and associated protection and control schemes.
EPT undertook design review co-ordination, Factory & Site Acceptance Testing & commissioning.
Victoria
May 2018 to present
As part of the REFCL program it was a requirement for HV customers were adequately protected from the newly installed Rapid Earth Fault Limiters. The solution involved 22/22kV isolation kiosks with a power transformer and associated protection and control schemes.
EPT undertook design review co-ordination, Factory & Site Acceptance Testing & commissioning.
![](https://static.wixstatic.com/media/399100_acf1621ff2ac4ce3b891eb9fb936e477~mv2.jpg/v1/fit/w_250,h_250,q_30,blur_30/399100_acf1621ff2ac4ce3b891eb9fb936e477~mv2.jpg)
![](https://static.wixstatic.com/media/399100_acf1621ff2ac4ce3b891eb9fb936e477~mv2.jpg/v1/fill/w_323,h_244,q_90/399100_acf1621ff2ac4ce3b891eb9fb936e477~mv2.jpg)
PLQ iPASS upgrade Braemar & Blackwall
Factory Acceptance Testing
ABB Australia (for Powerlink Queensland)
Brisbane
2013 - 2014
The 275kV (Breaker and a half scheme) and 330kV (mesh configuration) Control Buildings were equiped to provide protection and control functionality in conjunction with iPASS primary equipment.
Scheme testing and commissioning involved IEC61850-8-1 and 9-2LE with non conventional instrument transformers.
ABB Australia (for Powerlink Queensland)
Brisbane
2013 - 2014
The 275kV (Breaker and a half scheme) and 330kV (mesh configuration) Control Buildings were equiped to provide protection and control functionality in conjunction with iPASS primary equipment.
Scheme testing and commissioning involved IEC61850-8-1 and 9-2LE with non conventional instrument transformers.